Saturday 11 June 2011

Platform follow-up

When I was up at Kirkby Stephen East this morning (see the 'blog' below) I put up a picture of work in progress and commented that things were moving so quickly now that it might be worth publishing an 'after' picture tomorrow so that you could see for yourselves.

No need to wait. Mike has just sent me some 'before' and 'after' shots covering progress today.

Here is how things were at the beginning of the day as the void between the platform extension walls was back filled.


and here's how things looked by 'knocking off' time after around 130 concrete sleeper beams had been laid. Impressive progress eh?